Year Master Descriptions
2017

Chagalesh Engineering Company - Imam Khomeini Airport City

An assessment of the quality of the outer covering of the underground steel pipelines in the gas supply network and the firewall network and the fuel transfer line by the PCM / ACVG method at Imam Khomeini (RA)

2017

Iranian Engineering and Industrial Inspection Company

Engineering and design of the cathodic protection system of the Kangan Petroplazar Company

2017

District 8 Gas Transmission Operations

Evaluation of the coating and the status of the cathodic protection and external corrosion protection of pipelines by DCVG / CIPS

2017

Tabriz Petrochemical Company

Making Polarization Coupons and Data Logger

2017

Farrooz Petrochemical Company

Intelligence of cathodic protection system of Faramarz Petrochemical Company, Bandar Imam (Phase I)

2017

District 8 Gas Transmission Operations

Evaluation of the coating and the status of the cathodic protection and external corrosion protection of pipelines by DCVG / CIPS

2017

Iranian Engineering and Industrial Inspection Company

Engineering and design of the cathodic protection system of the Kangan Petroplazar Company

2017

Chagalesh Engineering Company - Imam Khomeini Airport City

An assessment of the quality of the outer covering of the underground steel pipelines in the gas supply network and the firewall network and the fuel transfer line by the PCM / ACVG method at Imam Khomeini (RA)

2017

Farrooz Petrochemical Company

Intelligence of cathodic protection system of Faramarz Petrochemical Company, Bandar Imam (Phase I)

2017

Tabriz Petrochemical Company

Making Polarization Coupons and Data Logger

2017

District 8 Gas Transmission Operations

Evaluation of the coating and the status of the cathodic protection and external corrosion protection of pipelines by DCVG / CIPS

2017

Iranian Engineering and Industrial Inspection Company

Engineering and design of the cathodic protection system of the Kangan Petroplazar Company

2017

Chagalesh Engineering Company - Imam Khomeini Airport City

An assessment of the quality of the outer covering of the underground steel pipelines in the gas supply network and the firewall network and the fuel transfer line by the PCM / ACVG method at Imam Khomeini (RA)

2016

Ilam Petrochemical Company - Tekin Ko Co.

PCM / ACVG test on 25 km Ilam petrochemical pipelines

2016

Maron Petrochemical Company - IEI

Test for 80 km of Ethan gas pipeline

2016

Yazd Power Generation Management Company

PCM / DCVG test of gas pipelines in Yazd Power Plant

2016

IOPTC

Monitoring and analyzing the risk of corrosion induced by the alternating current flow of oil pipelines

2016

District 10 Gas Transmission Operations

Survey of coating and cathodic protection system 413 km of gas pipelines in section 10 of DCVG / CIPS / C-Scan

2016

Arak Petrochemical Complex

Design and manufacture of 30 polarization coupons and data logger

2016

Arak Petrochemical Complex

Design and manufacture of 30 polarization coupons and data logger

2016

District 10 Gas Transmission Operations

Survey of coating and cathodic protection system 413 km of gas pipelines in section 10 of DCVG / CIPS / C-Scan

2016

IOPTC

Monitoring and analyzing the risk of corrosion induced by the alternating current flow of oil pipelines

2016

Yazd Power Generation Management Company

PCM / DCVG test of gas pipelines in Yazd Power Plant

2016

Maron Petrochemical Company - IEI

Test for 80 km of Ethan gas pipeline

2016

Ilam Petrochemical Company - Tekin Ko Co.

PCM / ACVG test on 25 km Ilam petrochemical pipelines

2015

Berna - POGC

Coverage and analysis of DC interference of gas pipelines 15 and 16 phases in Pars Oil and Gas Company by PCM / ACVG / CIPS methods

2015

Region 1 Gas Transmission Operations

Carrying out the study of the cathodic protection system and covering 90 km of the gas pipelines of the District 1 gas transmission company PCM / CIPS / DCVG

2015

Bandar Abbas Oil Refining Company

Performing an assessment of the pipeline cathodic protection system and inspecting the pipelines covering the Bandar Abbas Oil Refining Company with a length of 20 km using the PCM / ACVG method.

2015

Farrooz Petrochemical Company

Investigation of cathodic protection and the feasibility of intelligent cathodic protection system of Farroos Petrochemical Company, Bandar Imam

2015

Gas Company of Sistan and Baluchestan Province

Assessment and Inspection of the gas pipeline network coverage of Sistan-Baluchestan gas company by PCM / ACVG method