Year | Master | Descriptions |
---|---|---|
2017 | Chagalesh Engineering Company - Imam Khomeini Airport City |
An assessment of the quality of the outer covering of the underground steel pipelines in the gas supply network and the firewall network and the fuel transfer line by the PCM / ACVG method at Imam Khomeini (RA) |
2017 | Iranian Engineering and Industrial Inspection Company |
Engineering and design of the cathodic protection system of the Kangan Petroplazar Company |
2017 | District 8 Gas Transmission Operations |
Evaluation of the coating and the status of the cathodic protection and external corrosion protection of pipelines by DCVG / CIPS |
2017 | Tabriz Petrochemical Company |
Making Polarization Coupons and Data Logger |
2017 | Farrooz Petrochemical Company |
Intelligence of cathodic protection system of Faramarz Petrochemical Company, Bandar Imam (Phase I) |
2017 | District 8 Gas Transmission Operations |
Evaluation of the coating and the status of the cathodic protection and external corrosion protection of pipelines by DCVG / CIPS |
2017 | Iranian Engineering and Industrial Inspection Company |
Engineering and design of the cathodic protection system of the Kangan Petroplazar Company |
2017 | Chagalesh Engineering Company - Imam Khomeini Airport City |
An assessment of the quality of the outer covering of the underground steel pipelines in the gas supply network and the firewall network and the fuel transfer line by the PCM / ACVG method at Imam Khomeini (RA) |
2017 | Farrooz Petrochemical Company |
Intelligence of cathodic protection system of Faramarz Petrochemical Company, Bandar Imam (Phase I) |
2017 | Tabriz Petrochemical Company |
Making Polarization Coupons and Data Logger |
2017 | District 8 Gas Transmission Operations |
Evaluation of the coating and the status of the cathodic protection and external corrosion protection of pipelines by DCVG / CIPS |
2017 | Iranian Engineering and Industrial Inspection Company |
Engineering and design of the cathodic protection system of the Kangan Petroplazar Company |
2017 | Chagalesh Engineering Company - Imam Khomeini Airport City |
An assessment of the quality of the outer covering of the underground steel pipelines in the gas supply network and the firewall network and the fuel transfer line by the PCM / ACVG method at Imam Khomeini (RA) |
2016 | Ilam Petrochemical Company - Tekin Ko Co. |
PCM / ACVG test on 25 km Ilam petrochemical pipelines |
2016 | Maron Petrochemical Company - IEI |
Test for 80 km of Ethan gas pipeline |
2016 | Yazd Power Generation Management Company |
PCM / DCVG test of gas pipelines in Yazd Power Plant |
2016 | IOPTC |
Monitoring and analyzing the risk of corrosion induced by the alternating current flow of oil pipelines |
2016 | District 10 Gas Transmission Operations |
Survey of coating and cathodic protection system 413 km of gas pipelines in section 10 of DCVG / CIPS / C-Scan |
2016 | Arak Petrochemical Complex |
Design and manufacture of 30 polarization coupons and data logger |
2016 | Arak Petrochemical Complex |
Design and manufacture of 30 polarization coupons and data logger |
2016 | District 10 Gas Transmission Operations |
Survey of coating and cathodic protection system 413 km of gas pipelines in section 10 of DCVG / CIPS / C-Scan |
2016 | IOPTC |
Monitoring and analyzing the risk of corrosion induced by the alternating current flow of oil pipelines |
2016 | Yazd Power Generation Management Company |
PCM / DCVG test of gas pipelines in Yazd Power Plant |
2016 | Maron Petrochemical Company - IEI |
Test for 80 km of Ethan gas pipeline |
2016 | Ilam Petrochemical Company - Tekin Ko Co. |
PCM / ACVG test on 25 km Ilam petrochemical pipelines |
2015 | Berna - POGC |
Coverage and analysis of DC interference of gas pipelines 15 and 16 phases in Pars Oil and Gas Company by PCM / ACVG / CIPS methods |
2015 | Region 1 Gas Transmission Operations |
Carrying out the study of the cathodic protection system and covering 90 km of the gas pipelines of the District 1 gas transmission company PCM / CIPS / DCVG |
2015 | Bandar Abbas Oil Refining Company |
Performing an assessment of the pipeline cathodic protection system and inspecting the pipelines covering the Bandar Abbas Oil Refining Company with a length of 20 km using the PCM / ACVG method. |
2015 | Farrooz Petrochemical Company |
Investigation of cathodic protection and the feasibility of intelligent cathodic protection system of Farroos Petrochemical Company, Bandar Imam |
2015 | Gas Company of Sistan and Baluchestan Province |
Assessment and Inspection of the gas pipeline network coverage of Sistan-Baluchestan gas company by PCM / ACVG method |